Two cables — each six inches in diameter — are all it would take to connect vast amounts of new renewable energy from east of the Cascades to the population centers of Western Oregon and Southwest Washington. But even after lawmakers in both states approved laws to speed up the siting process, it could take three more years to obtain the regulatory approvals needed to begin building the Cascade Renewable Transmission project.
Both states have passed ambitious mandates to decarbonize the electric grid, Washington by 2030 and Oregon by 2035. The mandates have contributed to a boom in wind and solar projects in Eastern Oregon and Washington, where wind and sun are plentiful. But getting that power to cities west of the Cascades is increasingly constrained by the limits of the region’s existing transmission grid.
The proposed Cascade Renewable Transmission project would eliminate that bottleneck relatively quickly and inexpensively — by burying a pair of high-capacity copper cables 10 feet below the bottom of a shipping channel in the Columbia River. The transmission line would be capable of carrying 1,320 megawatts of power using DC current. It would run from The Dalles to Northwest Portland’s Harborton substation, 98 miles in all, at a cost of about $2 billion. The cables would cross dry land twice, underground: in Skamania County to avoid the Bonneville Dam and again in North Portland to avoid disturbing riverbed sediments at a Superfund site on the Willamette River.
Project backers have signed a letter of understanding with the Columbia Pacific Building Trades Council that they intend to sign a project labor agreement, a commitment to employ union construction labor. The project would amount to about four years of work for 300 to 400 construction workers. Most of the work would be building AC-DC converter stations at each end and laying cables where they cross land, including 7.6 miles of underground cable in Skamania County.

The riverbed work would be performed by a machine called a hydroplow. Towed by a barge or ship, the plow blade can insert 1 to 1.5 miles of cable per day. The work would take place from November to February over a two-year period, in compliance with rules that prohibit disturbing the river bottom when migratory fish are present in the river.
On Nov. 16, the Washington Energy Facility Site Evaluation Council (EFSEC) held a hearing in Washougal on the project.
“There isn’t enough transmission capacity to meet energy demand, much less the renewable clean energy demand,” testified Chris Hocker, vice president of PowerBridge, one of the project backers. “We’re convinced that submarine cable technology, which is used around the world, is safe and reliable.”
PowerBridge has previously installed underwater transmission lines in New York and New Jersey.
Technically the hearing was to get public input on whether the project complies with local land use plans and zoning ordinances. But none of the roughly 20 commenters mobilized by Friends of the Columbia Gorge addressed that. Instead, they voiced opposition to the project, citing concerns about the impact of electromagnetic fields on fish, whether the cables would heat the water, and the harm to invertebrates from disturbing riverbed sediment that might contain toxins.
Those concerns were addressed in the draft application for site certification, hundreds of pages filling three thick binders at the hearing sign-in table. Riverbed sediment tests along the planned route have shown no particular presence of toxins in the channel, which is already dredged periodically to maintain the shipping lane. Electromagnetic radiation and power line heat loss would be negligible through 10 feet of sediment.
EFSEC already held land use consistency hearings on the project last November, but the nonprofit Friends of the Columbia Gorge complained that those were premature because only a draft application had been submitted and some members of the council hadn’t been appointed. On Nov. 16, attorneys for the group submitted nine pages of procedural objections saying EFSEC hadn’t given enough public notice for the new round of hearings and that it should conduct a land use consistency hearing and an informational public hearing as separate events.
At the hearing, two building trades union leaders spoke in favor of the project.
“Over the past several years, there’s been concerted efforts to increase electrical demand while decreasing fossil fuel demand. This project is a step in that direction,” said Randall Friesen, executive secretary-treasurer of the Columbia Pacific Building Trades Council. “A lot of the familiar faces I see here tonight are anti build anything, and that’s just not a viable solution to the issues that we’re seeing.”
Nate Stokes, assistant business manager at Operating Engineers Local 701, said the Cascade Renewable Transmission project is a much quicker way to build transmission lines than overland projects like the Boardman to Hemingway project, a line running from Idaho to Boardman, Oregon, that took close to 20 years to get regulatory approval.
“If we really need to get transmission going, this is an alternative,” Stokes said. “Cascade Renewable is doing the right thing.”
The Army Corps of Engineers is expected to complete its draft Environmental Impact Statement in the first quarter of 2027 and finalize that by the end of 2027. Construction would likely begin in 2028 and last through 2032.